Question: Question content area Part 1 Development of Version 2 . 0 of a particular accounting software product is being considered by Jose Noguera's technology firm

Question content area
Part 1
Development of Version 2.0 of a particular accounting software product is being considered by Jose Noguera's technology firm in Baton Rouge. The activities necessary for the completion of this project are listed in the following table:
Activity
Normal Time(weeks)
Crash Time(weeks)
Normal Cost
Total Cost with Crashing
Immediate Predecessor(s)
A
44
33
$ 2 comma 000$2,000
$ 2 comma 600$2,600
long dash
B
22
11
$ 2 comma 100$2,100
$ 2 comma 800$2,800
long dash
C
33
33
$ 500$500
$ 500$500
long dash
D
88
44
$ 2 comma 400$2,400
$ 2 comma 700$2,700
A
E
66
33
$ 800$800
$ 1 comma 250$1,250
B
F
33
22
$ 3 comma 400$3,400
$ 4 comma 600$4,600
C
G
44
22
$ 1 comma 500$1,500
$ 2 comma 000$2,000
D, E
Part 2
a) Based on the given information regarding the activities for the project, the project length= enter your response here weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!