Question: Question F ( 2 0 points ) - RMS , EDF, DMS Scheduling: Provide a periodic task set, having three tasks, that is schedulable by
Question F points RMS EDF, DMS Scheduling:
Provide a periodic task set, having three tasks, that is schedulable by EDF, but
not by RMS Support your answer with necessary schedulability analysis or
schedule.
If the deadline is not equal to the task period eg relative deadline is less than the
period RMS is not an optimal static priority algorithm. Show this by means of
an example. That is construct a task set which is not RMschedulable, but is
schedulable by some other algorithm that considers "relative deadline" for
priority assignment.
Hint: Choose a task set that is schedulable by Deadline Monotonic Scheduling
DMS algorithm, but not by RMS algorithm.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock