Question: Question: Following task, predecessors, and duration (not the two columns): Construct CPM network diagram using the activity on arrow . a) For each task, give

Question: Following task, predecessors, and duration (not the two columns):

Question: Following task, predecessors, and duration (not the two columns): Construct CPMConstruct CPM network diagram using the activity on arrow.

a) For each task, give the Earliest Start, Latest Star, Earliest Finish, Latest Finish, and Total Float.

b) Sequence of tasks makes up the critical path? Include any dummy activities.

c) Total duration of the project as planned?

\begin{tabular}{|l|c|c|c|c|c|} \hline \multicolumn{1}{|c|}{ Task } & Predecessors & Duration & Task & Predecessors & Duration \\ \hline A & & 6 & N & K & 9 \\ \hline B & & 7 & O & L & 5 \\ \hline C & B & 5 & P & O & 7 \\ \hline D & A, C & 10 & Q & M & 20 \\ \hline E & D, I & 16 & R & M & 10 \\ \hline F & & 9 & S & R & 12 \\ \hline G & F & 11 & T & R & 10 \\ \hline H & & 10 & U & N, P, T & 8 \\ \hline I & G, H & 18 & V & U & 9 \\ \hline J & E & 8 & W & Q, S, V & 10 \\ \hline K & E & 5 & X & Q, S & 6 \\ \hline L & E & 8 & Y & X & 8 \\ \hline M & J & 8 & Z & Q & 5 \\ \hline \end{tabular}

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!