Question: Question Help Activity Ron a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18,

 Question Help Activity Ron a CPM network has predecessors M and
N, and has successor S. R has duration 5. N's late finish

Question Help Activity Ron a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M'sis 20. S's late start is 22. Which of the following is definitely true? Activity Ron a CPM network has predecessors Mand N, and has successor S. R has duration 6. N's lato finish is 18, while M's is 20. S's late start is 22. Which of the following is definitely true? O A. Ris critical and has zero slack. OB. N is a critical activity OC. The set of times cannot all be possible. OD. Rhos no slack but is not critical OE. S is a critical activity

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!