Question: Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while
Activity R on a CPM network has predecessors M and N, and has successor S. R has duration 5. N's late finish is 18, while M's is 20. S's late start is 22. Which of the following is definitelyTRUE?
Select one:
O A. Sis a critical activity.
O B. R has no slack but is not critical.
O C. Nis a critical activity.
O D. R is critical and has zero slack.
O E. The set of times cannot all be possible.