Question: Activity R on a CPM network has predecessors M and N , ?and has successor S . ?R has duration 5 . ?N ' s
Activity R on a CPM network has predecessors M and N ?and has successor S ?R has duration ?N s late finish is ?while M s is ?S s late start is ?Which of the following is definitely true?
Select one:
a ?N is a critical activity
b ?R has no slack but is not critical
c ?R is critical and has zero slack
d ?S is a critical activity.
e ?The set of times cannot all be possible.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock