Question: Question: In setting up a Kanban control system you need to determine the number of Kanban card sets needed. If the expected demand during lead

Question:

In setting up a Kanban control system you need to determine the number of Kanban card sets needed. If the expected demand during lead time is 50 per hour, the safety stock is 10% of the demand during lead time, the container size is 15. If the lead time to replenish an order is 8 hours, what number of Kanban card sets is needed?