Question: QUESTION 4 (20) The table below provides the duration estimates in days for a construction project. Predecessor Pessimistic Time 10 Activity A B D E

QUESTION 4 (20) The table below provides the

QUESTION 4 (20) The table below provides the duration estimates in days for a construction project. Predecessor Pessimistic Time 10 Activity A B D E F G H A,B E D,F G,F Optimistic Time 4 2 2 16 6 1 4 2 5 2 Most Likely Time 7 9 5 19 9 7 10 5 8 5 10 8 28 24 13 28 14 17 8 - HI 4.1 4.2 4.3 Determine the expected completion time for each activity. Construct an AON network for the activities of this contract. Determine the critical path for the project by calculating the slack for each activity