Question: Questions 1-3: Consider the Process Flow Diagram for bread-making with two parallel lines shown below. You are given that the cycle time for the mixing,
Questions 1-3: Consider the Process Flow Diagram for bread-making with two parallel lines shown below. You are given that the cycle time for the mixing, proofing, and packing operations is equal at hour per 100 loaves; and for the baking operation, the cycle time is 1 hour per 100 loaves. Assuming that the operation is staffed for a single 8 hour shift (with staggered start and end times for each operation) and that it is dedicated to producing a single product - white bread, answer the following questions:
A) What is the bottleneck operation in each bread making line (i.e., ignore the packing operation)?
B) Assuming that there are no constraints on materials supplies, what is the bottleneck operation in the complete line?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
