Question: Reference: Crashing - Table 1 To cut one day from the project's completion time, which activity should be crashed? (Hint: not all activities in the
Reference: Crashing - Table 1
To cut one day from the project's completion time, which activity should be crashed? (Hint: not all activities in the list are candidates for crashing at this step.)
| A. | C | |
| B. | A | |
| C. | B | |
| D. | D |