Question: RENDU OMBATHU A project being analyzed by PERT has 50 activities, 12 of which are on the critical path. If the estimated time along the

RENDU OMBATHU A project being analyzed by PERTRENDU OMBATHU

A project being analyzed by PERT has 50 activities, 12 of which are on the critical path. If the estimated time along the critical path is 156 days with a project variance of 121, the probability that the project will take 170 days or more to complete is A. near zero. B. 2.00. C. 0.1016. D. 0.8984. E. 0.0668