Question: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before
Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table:
| Activity | Immediate Predecessor(s) | Time (days) |
| A | minus | 33 |
| B | minus | 66 |
| C | minus | 11 |
| D | B | 1010 |
| E | A, D | 33 |
| F | C | 55 |
| G | E, F | 1212 |
This exercise contains only parts b, c, and d.
b) The critical activities for the leadership training program development project are
B - D - E - G
.
c) The project length for the leadership training program development project =
d) Slack time for each of the activities is:
| Activity | Slack Time |
| A B C D E F G |
|