Question: Roger works as a project manager and uses Microsoft Project to carry out his work. After updating a project schedule, he wants to determine the
Roger works as a project manager and uses Microsoft Project to carry out his work. After updating a project schedule, he wants to determine the amount of time that the schedule has shifted from the originally scheduled date. He needs a graphical view that shows the current schedule to baseline. Which of the following views should he use? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Gantt Chart option B Tracking Gantt option C Task Usage option D Network Diagram
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
