Question: Scenario C: Suppose you have a three-task sequence. All customers go to Task A. After task A, 20% of customers go to Task B; the

Scenario C: Suppose you have a three-task sequence. All customers go to Task A. After task A, 20% of customers go to Task B; the other 80% go to task C. After task B or C, all customers then go to Task D before leaving. There is an inventory buffer in between each station. Each buffer is empty at the start of each day.

Suppose throughput capacities are as follows. Task A: 30 customers/hour; task B: 10 customers/hour; task C: 20 customers/hour; task D, 32 customers/hour.

1. Refer to Scenario C. After 1 hour, how many units will be in the buffer between tasks A and B?

0

2

4

6

8

10

2. Refer to Scenario C. After 1 hour, how many units will be in the buffer between Tasks A and C?

0

2

4

6

8

10

3. Refer to Scenario C. What would the utilization of Task A be?

60%

70%

80%

90%

100%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!