Question: Scenario C: Suppose you have a three-task sequence. All customers go to Task A. After task A, 20% of customers go to Task B; the
Scenario C: Suppose you have a three-task sequence. All customers go to Task A. After task A, 20% of customers go to Task B; the other 80% go to task C. After task B or C, all customers then go to Task D before leaving. There is an inventory buffer in between each station. Each buffer is empty at the start of each day.
Suppose throughput capacities are as follows. Task A: 30 customers/hour; task B: 10 customers/hour; task C: 20 customers/hour; task D, 32 customers/hour.
1. Refer to Scenario C. After 1 hour, how many units will be in the buffer between tasks A and B?
0
2
4
6
8
10
2. Refer to Scenario C. After 1 hour, how many units will be in the buffer between Tasks A and C?
0
2
4
6
8
10
3. Refer to Scenario C. What would the utilization of Task A be?
60%
70%
80%
90%
100%
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts