Question: Schedule Building problems: Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please.
Schedule Building problems:
Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please.
1.
| Activity | Predecessors | Duration (months) |
| A | - | 3 |
| B | - | 2 |
| C | A | 5 |
| D | A | 3 |
| E | B,C | 4 |
| F | B,C | 2 |