Question: Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please. 1. Activity Predecessors

Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please.

1.

Activity

Predecessors

Duration (months)

A

-

3

B

-

2

C

A

5

D

A

3

E

B,C

4

F

B,C

2