Question: Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please. Activity Predecessors Duration
Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please.
| Activity | Predecessors | Duration |
| A | - | 10 |
| B | A | 8 |
| C | A | 12 |
| D | C | 0 |
| E | B,D | 18 |
| F | E | 16 |