Question: Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please. Activity Predecessors Duration

Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please.

Activity

Predecessors

Duration

A

-

10

B

A

8

C

A

12

D

C

0

E

B,D

18

F

E

16