Question: Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please. 2. Activity Duration
Please build the schedule and complete a forward and backward pass. Label the Critical Path and the Duration of the project, please.
2.
| Activity | Duration | Predecessors |
| A | 5 days | None |
| B | 4 days | None |
| C | 8 days | A |
| D | 11 days | A, B |
| E | 1 day | C |
| F | 1 day | D |
| G | 6 days | E, F |
| H | 4 days | G |
| I | 12 days | G |
| J | 2 days | L |
| K | 9 days | I, J |
| L | 4 days | H |