Question: Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B TIME (WEEKS) 2 D E F G H B CD D F EG 5

Schedule the following activities using CPM:

Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B TIME (WEEKS) 2 D E F G H B CD D F EG 5 4 3 4 1 1 2 b. What is the critical path? A-B-D-F-G-H A-B-D-E-H O A-C-E-F-G-H O A-C-E-G-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OB. 3 weeks ; C. 1 week ;F. 4 weeks. OB. 1 week iH. 3 weeks: F. 2 weeks. OC. 4 weeks ;F. 2 weeks: G. 2 weeks