Question: Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B D E F G H A B C D D F EG TIME (WEEKS)

Schedule the following activities using CPM:
Schedule the following activities using CPM:
Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B D E F G H A B C D D F EG TIME (WEEKS) 2 5 6 3 9 5 3 6 0 b. What is the critical path? O A-B-D-E-H O A-B-E-H O A-C-E-F-G-H O A-C-E-H c. How many weeks will it take to complete the project? Number of weeks d. Which activities have slack, and how much? OC, 2 weeks Picture F. 1 week Picture G. 1 week. OB. 3 weeks Picture D. 2 weeks. O E, 2 weeks Picture H. 1 week