Question: Problem 5-8 (Algo) Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B D TIME (WEEKS) 3 2 5 6 A A B Cmediacm.png

Problem 5-8 (Algo) Schedule the following

Problem 5-8 (Algo) Schedule the following activities using CPM: IMMEDIATE PREDECESSOR ACTIVITY A B D TIME (WEEKS) 3 2 5 6 A A B Cmediacm.png D D E F G UAARU 2 3 5 Etmedia.om.png G b. What is the critical path? OA-C-E-F-G-H O A-B-D-F-G-H OA-C-E-H O A-C-E-G-H c. How many weeks will it take to complete the project? Number of weeks