Question: Schedule the following activities using CPM: table [ [ ACTIV VITY , IMMEDIATE PREDECESSOR,TIME, ( WEEKS ) ] , [ A , - ,

Schedule the following activities using CPM:
\table[[ACTIVVITY,IMMEDIATE PREDECESSOR,TIME,(WEEKS)],[A,-,,3],[B,A,,4],[C,A,,5],[D,B,,4],[E,C%media:cm.png%[,,8],[F,D,,6],[G,F,,4],[H,E%media:cm.png%,,5]]
b. What is the critical path?
A-B-D-F-G-H
A-C-E-F-G-H
A-B-D-E-H
A-B-E-H
c. How many weeks will it take to complete the project?
Number of weeks
 Schedule the following activities using CPM: \table[[ACTIVVITY,IMMEDIATE PREDECESSOR,TIME,(WEEKS)],[A,-,,3],[B,A,,4],[C,A,,5],[D,B,,4],[E,C%media:cm.png%[,,8],[F,D,,6],[G,F,,4],[H,E%media:cm.png%,,5]] b. What is