Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME, ( WEEKS ) ] , [ A , - , ,

Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME,(WEEKS)],[A,-,,5],[B,A,,3],[C,A,,4],[D,B,,6],[E,C,D,,8],[F,D,,2],[G,F,,4],[H,E,G,,3]]
b. What is the critical path?
A-C-E-F-G-H
A-B-D-E-H
A-C-E-H
A-B-D-F-G-H
 Schedule the following activities using CPM: \table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME,(WEEKS)],[A,-,,5],[B,A,,3],[C,A,,4],[D,B,,6],[E,C,D,,8],[F,D,,2],[G,F,,4],[H,E,G,,3]] b. What is