Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME, ( WEEKS ) ] , [ A , - , ,
Schedule the following activities using CPM:
tableACTIVITYIMMEDIATE PREDECESSOR,TIME,WEEKSABACADBEFDGFH
b What is the critical path?
ACEFGH
ABDEH
ACEH
ABDFGH