Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE,TIME ( WEEKS ) ] , [ A , PREDECESSOR, 2 ] ,

Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE,TIME (WEEKS)],[A,PREDECESSOR,2],[B,-,5],[C,A,6],[D,A,3],[E,B,9],[F,B-C,5],[G,D,3],[H,F,6]]
Requirement 1:
What is the critical path?
(Click to select)vv
Requirement 2:
How many weeks will it take to complete the project?
Number of weeks
Requirement 3:
Which activities have slack?
(Click to select)
 Schedule the following activities using CPM: \table[[ACTIVITY,IMMEDIATE,TIME (WEEKS)],[A,PREDECESSOR,2],[B,-,5],[C,A,6],[D,A,3],[E,B,9],[F,B-C,5],[G,D,3],[H,F,6]] Requirement 1: What