Question: Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR,TIME ( WEEKS ) ] , [ A , - , 5

Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,5],[B,A,3],[C,A,4],[D,B,6],[E,C%media:cm.png% D,8],[F,D,2],[G,F,4],[H,E%media:cm.png% G,3]]
b. What is the critical path?
A-B-D-E-H
A-B-D-F-G-H
A-C-E-H
A-C-E-F-G-H
c. How many weeks will it take to complete the project?
Number of weeks
d. Which activities have slack, and how much?
B,1 week; H,2 weeks; F,4 weeks.
C,5 weeks; F,2 weeks; G,2 weeks.
A,2 weeks; C,3 weeks; F,1 week.
 Schedule the following activities using CPM: \table[[ACTIVITY,IMMEDIATE PREDECESSOR,TIME (WEEKS)],[A,-,5],[B,A,3],[C,A,4],[D,B,6],[E,C%media:cm.png% D,8],[F,D,2],[G,F,4],[H,E%media:cm.png% G,3]]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!