Question: Scheduling, AOA (Using Linear Programming to Find a Critical Path) Tasks Precedence Time A - 6 weeks B - 4 weeks C - 3 weeks
| Tasks | Precedence | Time |
| A | - | 6 weeks |
| B | - | 4 weeks |
| C | - | 3 weeks |
| D | a | 4 weeks |
| E | b | 3 weeks |
| F | b | 2 weeks |
| G | c | 3 weeks |
| H | d,e | 2 weeks |
| I | f | 1 week |
| J | g,i | 2 weeks |