Question: Scheduling: Given the following project data: a ) Draw the project network b ) Calculate total floats and determine the critical path c ) What

Scheduling:
Given the following project data:
a) Draw the project network
b) Calculate total floats and determine the critical path
c) What is the effect of delaying activity G by 6 days?
d) What is the overall percent complete of the project, to-date?