Question: Scott is managing a project which is starting to fall behind. From earlier discussions, he knows that management wants all the deliverables exactly as was

Scott is managing a project which is starting to fall behind. From earlier discussions, he knows that management wants all the deliverables exactly as was identified in the project scope. Top management is willing to invest additional resources to help with the project time line. With additional resources available to shorten the schedule, how should the target date be classified for this project's priority matrix? Group of answer choices Accept Constrain Enhance Limit