Question: See Schedule for Due Date Activity Predecessor Duration A -- 6 B -- 4 C A 5 D B 7 E B 8 F C

See Schedule for Due Date

Activity

Predecessor

Duration

A

--

6

B

--

4

C

A

5

D

B

7

E

B

8

F

C

4

G

D, E

5

H

E

9

I

F, G, H

3

  1. What is the total duration?

  1. What is the total float of the Critical Path?

  1. What is the Critical Path?

  1. What is the latest that activity F can start without affecting its completion date?

  1. What is the earliest activity G can finish?

  1. What is the Late Finish of Activity D?

SHOW WORK