Question: See Schedule for Due Date Activity Predecessor Duration A -- 6 B -- 4 C A 5 D B 7 E B 8 F C
See Schedule for Due Date
| Activity | Predecessor | Duration |
| A | -- | 6 |
| B | -- | 4 |
| C | A | 5 |
| D | B | 7 |
| E | B | 8 |
| F | C | 4 |
| G | D, E | 5 |
| H | E | 9 |
| I | F, G, H | 3 |
- What is the total duration?
- What is the total float of the Critical Path?
- What is the Critical Path?
- What is the latest that activity F can start without affecting its completion date?
- What is the earliest activity G can finish?
- What is the Late Finish of Activity D?