Question: Setup Cost = $777 per setup Holding cost = $0.16 per unit per week Lead Time = 1 Week Safety Lead Time = 1 Week
Setup Cost = $777 per setup
Holding cost = $0.16 per unit per week
Lead Time = 1 Week
Safety Lead Time = 1 Week
Lot Size = LFL (Lot-for-Lot)
Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirements 453 425 501 678 668 591 607 680 700 662 608 566 Scheduled Receipts 455 Beg. Inventory 875 Net Requirements Ending Inventory Planned Order Receipts Planned Order Releases What are your Planned Order Releases for Week 5?