Question: Setup Cost = $795 per setup Holding cost = $0.45 per unit per week Lead Time = 1 Week Lot Size = LFL Week 1

Setup Cost = $795 per setup Holding cost = $0.45

Setup Cost = $795 per setup Holding cost = $0.45 per unit per week Lead Time = 1 Week Lot Size = LFL Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirements 561 584 551 410 553 424 500 475 544 444 440 519 Scheduled Receipts Beg. Inventory 852 Net Requirements Ending Inventory Planned Order Receipts Planned Order Releases If you have a required safety stock of 182 units, indicate your Net Requirements for Week 4