Question: Setup Cost = $690 per setup Holding cost = $0.33 per unit per week Lead Time = 1 Week Lot Size = LFL (Lot-for-Lot) Week
Setup Cost = $690 per setup
Holding cost = $0.33 per unit per week
Lead Time = 1 Week
Lot Size = LFL (Lot-for-Lot)
Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirements 590 542 543 496 465 436 561 499 555 530 597 541 Scheduled Receipts Beg. Inventory 824 Net Requirements Ending Inventory Planned Order Receipts Planned Order Releases If you have a required safety stock of 149 units, indicate your Net Requirements for Week 2.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts