Question: Setup Cost = $642 per setup Holding cost = $0.48 per unit per week Lead Time = 1 Week Lot Size = LFL (Lot-for-Lot) Week
Setup Cost = $642 per setup
Holding cost = $0.48 per unit per week
Lead Time = 1 Week
Lot Size = LFL (Lot-for-Lot)
Week 1 2 3 4 5 6 7 8 9 10 11 12 Gross Requirements 582 589 514 595 437 595 490 570 571 586 577 558 Scheduled Receipts Beg. Inventory 801 Net Requirements Ending Inventory Planned Order Receipts Planned Order Releases If you have a required safety stock of 123 units, indicate your Net Requirements for Week 2.