Question: Setup Cost = $771 per setup Holding cost = $0 per unit per week Lead Time = 1 Week Safety Lead Time = 1 Week

Setup Cost = $771 per setup Holding cost = $0 per

Setup Cost = $771 per setup Holding cost = $0 per unit per week Lead Time = 1 Week Safety Lead Time = 1 Week Scrap Allowance = 7.8% Lot Size = LFL (Lot-for-Lot) Week 1 12 3 4 5 6 6 7 8 9 10 11 12 Gross Requirements 412 410 551 686 530 504 560 547 600 552 633 564 Scheduled Receipts 479 Beg. Inventory 724 Net Requirements Ending Inventory Planned Order Receipts Planned Order Releases What are your Planned Order Releases for Week 5? Round up to a whole unit