Question: 12) Setup Cost = $609 per setup Holding cost = $0.24 per unit per week Lead Time = 1 Week Lot Size = LFL Week
12) Setup Cost = $609 per setup
Holding cost = $0.24 per unit per week
Lead Time = 1 Week
Lot Size = LFL
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| Gross Requirements | 425 | 441 | 456 | 544 | 471 | 455 | 527 | 563 | 516 | 571 | 473 | 462 |
| Scheduled Receipts | ||||||||||||
| Beg. Inventory | 881 | |||||||||||
| Net Requirements | ||||||||||||
| Ending Inventory | ||||||||||||
| Planned Order Receipts | ||||||||||||
| Planned Order Releases |
If you have a required safety stock of 191 units, indicate your Net Requirements for Week 4.
13) Setup Cost = $701 per setup
Holding cost = $0.2 per unit per week
Lead Time = 1 Week
Lot Size = LFL (Lot-for-Lot)
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
| Gross Requirements | 559 | 418 | 567 | 453 | 403 | 428 | 496 | 508 | 549 | 530 | 574 | 427 |
| Scheduled Receipts | ||||||||||||
| Beg. Inventory | 871 | |||||||||||
| Net Requirements | ||||||||||||
| Ending Inventory | ||||||||||||
| Planned Order Receipts | ||||||||||||
| Planned Order Releases |
If you have a required safety stock of 198 units, indicate your Net Requirements for Week 2.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts