Question: Show all your work ( typed in the document or pasting a scanned image of your handwritten solution ) . Save your solution document in
Show all your work typed in the document or pasting a scanned image of your handwritten solution Save your solution document in a pdf file and upload it to Canvas along with an Excel file for calculations performed in Excel.
Problem points
The following table lists the components needed to assemble an end item, lead times, and quantities on hand.
a If units of the end item are to be assembled, how many additional units of E are needed? Hint You don't need to develop an MRP plan to determine this.
b An order for the end item is scheduled to be shipped at the start of week What is the latest week that the order can be started and still be ready to ship on time? Hint You don't need to develop an MRP plan for this part either.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock