Question: Social Project manager is faced with a project with the following activities: Activity-ID Description Duration 1-2 Social Work Team to live in Village 5 Weeks

Social Project manager is faced with a project with the following activities:

Activity-ID Description Duration

1-2 Social Work Team to live in Village 5 Weeks

1-3 Social Research Team to do survey 12 Weeks

3-4 Analyze results of survey 5 Weeks

2-4 Establish Mother & Child Health Program 14 Weeks

3-5 Establish Rural Credit Program 15 Weeks

4-5 Carry out Immunization of Under Fives 4 Week

Find the Critical Path and the Project Duration.