Question: Social Project manager is faced with a project with the following activities: Activity-ID Description Duration 1-2 Social Work Team to live in Village 5 Weeks
Social Project manager is faced with a project with the following activities:
Activity-ID Description Duration
1-2 Social Work Team to live in Village 5 Weeks
1-3 Social Research Team to do survey 12 Weeks
3-4 Analyze results of survey 5 Weeks
2-4 Establish Mother & Child Health Program 14 Weeks
3-5 Establish Rural Credit Program 15 Weeks
4-5 Carry out Immunization of Under Fives 4 Week
Find the Critical Path and the Project Duration.