An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =49, LF C = 61; activity times are A = 4, B = 6, C = 8 O a. 41 O b. 43 O c. Insufficient information O d. 39 O e. 38 Next page