Question: An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40,

An activity, A, has two succeeding activities, B
An activity, A, has two succeeding activities, B and C. Given the following information, determine the latest starting time for activity A. EF B =40, EF C = 42, LF B =50, LF C = 59; activity times are A = 4, B = 6, C = 8 a. 39 b. 44 c. 42 Od Insufficient information e. 40