Question: SOLVE QUESTION NUMBER 22 (AON), THEN ATTACH YOUR WORK HERE ONLY THE NETWORK DIAGRAM WILL BE ACCEPTED The table below shows the complete project plan

SOLVE QUESTION NUMBER 22 (AON), THEN ATTACH YOUR

SOLVE QUESTION NUMBER 22 (AON), THEN ATTACH YOUR

SOLVE QUESTION NUMBER 22 (AON), THEN ATTACH YOUR WORK HERE ONLY THE NETWORK DIAGRAM WILL BE ACCEPTED The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each activity. ANSWER THE FOLLOWING QUESTION ACTIVITYIMMEDIATE DURATION PREDECESSOR A 3 B - 1 C A 2 D A 6 E B 2 I O TIM U F B 4 G 3 3 D,E,F C,D,G 4 I 1 I I J 6