Question: Some tasks have a single resource or multiple resources. When Fazila enters actual work values for the task or assignment that has a single resource,

Some tasks have a single resource or multiple resources. When Fazila enters actual work values for the task or assignment that has a single resource, Project: Question 10 options: If the actual work value is greater than the planned work, Project recalculates Remaining Work. Applies the actual work values equally to both the task and the resource assignment. If the actual work value is less than the planned work, Project sets the Remaining Work to zero. Distributes or rolls down the actual work values among to the assignments according to their assignment units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!