Question: Steps for How to solve Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR, table [ [ TIME ]

Steps for How to solve
Schedule the following activities using CPM:
\table[[ACTIVITY,IMMEDIATE PREDECESSOR,\table[[TIME],[(WEEKS)]]],[A,-,5],[B,A,3],[C,A,4],[D,B,6],[E,C%media:cm.png%,8],[F,D,2],[G,D,4],[H,Ermedia:cm.png%,3]]
b. What is the critical path?
A-B-D-F-G-H
A-B-D-E-H
A-C-E-F-G-H ?**
A-C-E-H
c. How many weeks will it take to complete the project?
Answer is complete but not entirely correct.
Number of weeks
26