Question: Steps for How to solve Schedule the following activities using CPM: table [ [ ACTIVITY , IMMEDIATE PREDECESSOR, table [ [ TIME ]
Steps for How to solve
Schedule the following activities using CPM:
tableACTIVITYIMMEDIATE PREDECESSOR,tableTIMEWEEKSABACADBECmedia:cmpngFDGDHErmedia:cmpng
b What is the critical path?
ABDFGH
ABDEH
ACEFGH
ACEH
c How many weeks will it take to complete the project?
Answer is complete but not entirely correct.
Number of weeks
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
