Question: [Study Guide - different numbers) A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated

[Study Guide - different numbers) A project being
[Study Guide - different numbers) A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 236.4 days or more to complete? near zero O 0.8413 O 2.14 O 0.1587 O 0.0126