Question: Study Guide - different numbers) A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated

Study Guide - different numbers) A project being

Study Guide - different numbers) A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 236.4 days or more to complete? 2.14 near zero 0.8413 00126 0.1587