Question: [Study Guide - different numbers] A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated

[Study Guide - different numbers] A project being
[Study Guide - different numbers] A project being analyzed by PERT has 60 activities, 13 of which are on the critical path. If the estimated time along the critical path is 214 days with a project variance of 100, what is the probability that the project will take 236.4 days or more to complete? 2.14 0.0126 near Zero 0.1587 0.8413

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!