Question: Study Problem 3 Activity A 4 B 5 C 2 D 2 E 6 F 3 G 1 Project Duration 1 0 9 8 7

Study Problem 3
Activity
A 4
B 5
C 2
D 2
E 6
F 3
G 1
Project Duration 10
9
8
7
6
Normal Crash Cost Time (wk.)
2,50024,00043,00012,00013,00042,00012,0001
Activity Crashed Normal
E
A
E, F
A, B
Normal Time (wk.)
Crash Cost 6,0005,0005,0003,0004,0005,0002,000
Project Cost 18,50019,00020,75022,75025,500
Slope ($/week)1,7501,0002,0001,0005001,500
- Maximum crash limit achieved because critical path crashed to their limit)
Project
Paths Normal Duration
E
A-E 109876
A-D-G 77665 A-C-F 99876 B-F88876
* Activity crashed to limit