Question: SUBJECT: OPERATION MANAGEMENT DO NOT USE MS EXCEL OR OTHER SOFTWARE TO CALCULATE THE ANSWER NO FURTHER DATA AVAILABLE 1 There are two jobs A

SUBJECT: OPERATION MANAGEMENT
DO NOT USE MS EXCEL OR OTHER SOFTWARE TO CALCULATE THE ANSWER
NO FURTHER DATA AVAILABLE
1 There are two jobs A and B, which are to be processed on six machines 1,2,3,4, and 5. The time required for these jobs and the technological order are as shown below. Time required (min) Job 1 2 3 4 5 A 25 35 15 20 30 B 15 20 35 15 25 Technological order Job A: 1-3-2-4-5 Job B: 2-1-3-4-5 Determine the optimum path using graphical methodStep by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock