Question: Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16

Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16 days. Determine the expected processing time for the activity.

a.3.16

b.5.16

c.5.83

d.5.33

Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16 days. Determine the variance associated with this activity.

a.1 day

b.2 days

c.3 days

d.4 days