Question: Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16
Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16 days. Determine the expected processing time for the activity.
a.3.16
b.5.16
c.5.83
d.5.33
Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16 days. Determine the variance associated with this activity.
a.1 day
b.2 days
c.3 days
d.4 days