Question: Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16

Suppose an activity has an optimistic processing

Suppose an activity has an optimistic processing time of 4 days, a most likely time of 10 days, and a pessimistic processing time of 16 days. Determine the expected processing time for the activity. O a. 3.16 O b. 5.16 O c. 5.83 O d. 5.33