Question: - Suppose that a task in a project has the following time estimates. to = optimistic completion time = 9 weeks = most likely completion

- Suppose that a task in a project has the
- Suppose that a task in a project has the following time estimates. to = optimistic completion time = 9 weeks = most likely completion time = 17 weeks tp = pessimistic completion time = 18 weeks Compute the expected task completion time. The expected task completion time is weeks. (Enter your response rounded to one decimal place)